R (Smar Holdings Ltd) v Secretary of State for Environment, Foor and Rural Affairs [2025] EWCA Civ 1041

Share This Post

What the case was about

Smar Holdings unlawfully felled trees on land in Keynsham without a felling licence, triggering a restocking notice (RSN) under s.17A Forestry Act 1967. On appeal to the Secretary of State, Smar argued:

  1. ย The land was proposed for housing allocation in an emerging local plan.
  2. ย It would be in the public interest to modify the RSN so the trees could later be removed if planning permission was granted.
  3. ย Alternatively, the restocking should take place on different land.
  4. ย The committeeโ€™s process was unfair due to involvement of a Forestry Commission official in ministerial briefing.

The High Court had agreed with Smar and quashed the decision. The Secretary of State appealed.

What the Court of Appeal decided

1. Planning considerations are not relevant to restocking decisions

This is the key point and the reason the Secretary of State won.

The Court of Appeal held:

  • The Forestry Act regime exists to protect and maintain national forestry resources.
  • The planning system is separate.
  • Parliament created only two explicit โ€œjoin pointsโ€: s.9(4)(d) (felling needed for development with full planning permission) s.15 (interface with TPOs).
  • Beyond those, planning merits (housing need, allocations, public interest) are irrelevant when deciding whether a restocking notice should stand.

So the Secretary of State was not required โ€” and indeed not permitted โ€” to take into account the public interest in housing delivery or emerging allocations.

This overturns the High Court’s core reasoning.

2. Smarโ€™s proposed modification to the RSN was lawfully rejected

Smar wanted to insert a clause allowing the restocked trees to be removed automatically โ€œif planning permission is later grantedโ€.

The Court said:

  • That would undermine the felling control regime.
  • It would pre-empt the Forestry Commissionโ€™s enforcement discretion.
  • It could distort future planning decisions by allowing unlawful felling to influence the baseline.

Therefore, rejecting the modification was entirely rational.

3. Alternative-site restocking: a permissible consideration, but Smar provided no evidence

The Court said:

  • Restocking on alternative land can be relevant under s.17A because the statute expressly allows it.
  • BUT the landowner must provide evidence of suitability.
  • Smar offered almost nothing โ€” no silvicultural justification, no equivalence data, nothing.

So the committee was entitled to reject the alternative-land proposal.

4. Alleged procedural unfairness (Ground 4) โ€” inappropriate, but not fatal

A Forestry Commission official, who served as secretary to the reference committee, submitted briefing to the Minister recommending acceptance of the committeeโ€™s report.

The Court held:

  • That was inappropriate, because the Commission was a party to the dispute.
  • But: no material prejudice resulted because all the relevant issues turned on points of law, and Smarโ€™s arguments on those points failed in principle.

So the decision wasnโ€™t quashed on procedural grounds.

Overall outcome

Appeal allowed.

High Court judgment overturned.

Smarโ€™s judicial review dismissed.

The Court of Appeal restored the Secretary of Stateโ€™s original decision upholding the restocking notice.

Key principles coming out of the case

A. Planning merits (including housing delivery) are irrelevant to felling-control decisions

Only forestry-related factorsโ€”good forestry, amenity, silviculture, maintaining reservesโ€”can be taken into account.

B. Developers who โ€œjump the gunโ€ by felling early must live with the consequences

If you want to rely on the s.9(4)(d) exemption, you must wait until you have a full planning permission (or outline with reserved matters approved).

C. Proposed developmentโ€”even a draft allocationโ€”does not dilute restocking duties

Emerging planning documents have no relevance to the Forestry Act regime.

D. Alternative-land restocking needs proper evidence

Vague suggestions will not succeed.

Why this case matters (practically)

  • It shuts down arguments that planning need or housing benefit can justify modifying or avoiding RSNs.
  • It reinforces the disincentive for developers to fell early.
  • It underlines that felling-control decisions must remain insulated from planning pressures.
  • It ensures that unlawful felling cannot be retrospectively โ€œfixedโ€ by leaning on future development prospects.

For anyone operating in the overlap between trees and planning (so, you!), this is now pretty definitive authority.

author avatar
Sarah Dodd

Recents Posts

Share This Post

Environmental

Felling Licence – Who needs one?

When Do You Need a Felling Licence? If youโ€™re planning to cut down trees in the UK, one of the first legal questions you should

Environmental

Subsidence: The Origin Story

The meaning of subsidence (at least in the insurance and legal context) owes far more to post-war lending practices and reputational risk than to geotechnical

x  Powerful Protection for WordPress, from Shield Security
This Site Is Protected By
Shield Security