New tree root subsidence judgment: POV of the tree owner

The County Court decision in Kevin Roger Jones and Tracey Ann Jones v Middlesbrough Borough Council, handed down on 29 September 2026, illustrates the consequences of an inadequate response to developing evidence. It also provides useful lessons for councils, housing providers and other organisations managing trees alongside property risks.

The decision applied established principles of foreseeability, reasonableness and causation. Its significance for tree owners lies in the practical handling of this particular claim, rather than in any general requirement to remove trees when an allegation is received.

Distinguishing an allegation from a foreseeable risk

The first material letter to the council, dated 5 May 2016, described its trees as a potential future risk. The accompanying arboricultural assessment identified vegetation belonging to the homeowners as the apparent cause of the existing damage. The judge did not consider that correspondence sufficient to make damage from the council’s trees reasonably foreseeable.

That finding is an important part of a balanced reading of the case. The law does not impose liability simply because a tree could cause subsidence in some circumstances. Berent v Family Mosaic Housing [2012] EWCA Civ 961 connects the assessment of foreseeable risk with the question of what action is reasonable. The risk, potential consequences and practicable response must be considered together.

However, the information available to the council changed. A letter of 13 September 2016 enclosed monitoring results and attributed continuing movement to its trees. Considered with the other circumstances, that evidence established a real risk which the council should have recognised. An organisation therefore needs a process for revisiting an assessment when further evidence arrives.

Assessing the evidence in its current context

The homeowners had removed their own vegetation in April 2016, but movement continued. The judge concluded that the council should have inspected and formed an independent view of the situation on the ground. Continuing to rely on the earlier assessment, without adequately investigating the changed position, was insufficient.

For tree owners, this is a useful distinction between requesting evidence and engaging with evidence. Further information may properly be needed before a decision is made. The organisation should nevertheless identify what remains uncertain, whether it can resolve that uncertainty itself and when the position will be reviewed.

The judgment also demonstrates why root identification cannot always be treated as the only relevant evidence. The court considered monitoring, the removal of other vegetation, expert opinion and the wider history. It found that the council’s trees were the effective and substantial cause of the new and ongoing damage.

As Jones explains when citing Loftus-Brigham v London Borough of Ealing [2003] EWCA Civ 1490, a material contribution to damage may be sufficient for causation. A tree need not be the only cause. That does not make every contribution legally actionable: foreseeability, breach and the recoverable consequences still require separate consideration.

Making responsibility clear within the organisation

The council’s arrangements divided tree responsibilities between different departments. The judge criticised the absence of clear ownership and coordination, and urged review of those arrangements. The court also found that no inspections had been undertaken and that the council had not followed the basic inspection regime in its own policy.

An inspection policy can support sound management only if responsibility for implementing it is clear and records show what has been done. It is also necessary to distinguish routine inspection from the investigation required when a specific property-damage allegation is received. A routine safety inspection does not necessarily answer the subsidence questions raised by a claim.

A practical response should identify who coordinates the matter, who reviews engineering and arboricultural evidence, who authorises work and who communicates decisions. Those roles may sit with different people, but the overall response needs someone responsible for ensuring that it progresses.

Selecting a proportionate management strategy

The measured approach explained in Leakey v National Trust [1980] QB 485, discussed in the judgment and in our practical guide to tree root subsidence claims, helps place this decision in context. Although Leakey concerned a natural land hazard rather than subsidence from roots, it explains that the duty is to take steps reasonable in the circumstances to prevent or minimise a known risk. The scale of the risk, likely consequences, practicability, cost and time available for action inform that assessment. Receiving a claim therefore calls for an informed assessment of the particular risk and available responses.

The court did not treat removal of every tree as the only possible response from the outset. It accepted evidence that selective removal with monitoring should have commenced by summer 2017. The evidence also addressed management of the remaining vegetation and the potential for regrowth.

The council removed two trees in March 2018. The difficulty was that there was no corresponding documented programme of inspection, management or maintenance. The judge found that the overall risk had not been addressed coherently.

For a staged strategy, the reasoning needs to extend beyond the first intervention. Which trees are being addressed, and why? How will the remaining vegetation be managed? What monitoring will show whether the strategy is working? What would trigger a further intervention? Those questions help make a proportionate response both workable and reviewable.

Such a strategy requires appropriate technical advice. The judgment does not establish that pruning is always effective, that removal of a particular number of trees will stabilise a building or that all retained vegetation needs the same maintenance regime. The appropriate response depends on the site and the evidence.

Communicating an actionable proposal

In December 2017, the council’s insurer communicated agreement to remove trees as soon as possible, without specifying a date. The homeowners were not subsequently notified of the removal of two trees. The judge accepted that, given the density of the group, the removals were not readily apparent to them.

This matters because communication allows the parties to evaluate whether proposed works may resolve the problem. A useful proposal identifies the relevant trees, scope of work, intended timetable and arrangements for review. Confirmation of completed work should be sufficiently specific to inform the subsequent technical assessment.

Tree owners may face legitimate constraints, including access, procurement and any required consents. Those should be explained and reflected in a realistic programme. A statement of intention without a clear plan gives the homeowner and their advisers little basis for deciding whether continued waiting is reasonable.

Understanding the exposure to remedial costs

Delaware Mansions v Westminster City Council [2001] UKHL 55 provides the established framework for reasonable remedial expenditure arising from a continuing nuisance. The tree owner’s reasonable opportunity to address the problem is important, but that opportunity must be assessed against the actual history and the response.

In Jones, underpinning in August 2018 was found reasonable after continuing movement and an inadequate management response. The court also accepted earlier investigation costs as necessary parts of the evolving claim. The expenditure award was £59,647.87.

The result does not make a tree owner responsible for every cost incurred whenever action is delayed. The claimant must still establish the relevant legal elements and justify the expenditure. Equally, an organisation should not assume that offering some tree work will prevent recovery of stabilisation costs if the proposal does not adequately address the ongoing problem.

The court separately refused the £1,000 policy excess because it would have been incurred in any event. That finding illustrates the need to examine individual heads of loss rather than treating the overall claim as an indivisible demand.

Taking the homeowner experience into account

The judgment awarded each homeowner £2,200 for distress and inconvenience. Their evidence concerned continuing movement, visible cracking, uncertainty, delay and the disruption of works. The award was based on the circumstances proved, rather than a standard rate applicable to other claims.

For an organisation handling a claim, the practical lesson is to consider the experience of the people living with the damage alongside the technical investigation. Clear updates, explanations and realistic timescales can help them understand what is being done. They also provide a record of the organisation’s response.

Turning the lessons into a response process

A useful review of an existing procedure would ask whether incoming allegations are assigned promptly, technical uncertainties are identified, significant new evidence triggers reassessment and agreed actions have completion and review dates. Inspection records, work instructions and communications should be kept together so that the decision history can be understood.

The claim in Jones succeeded because of the findings about this evidence, this developing risk and this response. The broader operational lesson is to connect those elements. A proportionate approach protects the value of trees while addressing supported risks to neighbouring property, and it needs a clear plan, implementation and review to achieve that purpose.

Leaf it with us!

Got a legal question involving a tree?

Book a no-obligation advice call and talk it through with a specialist.

Similar Articles

Why choose Tree Law?

The UK’s only specialist tree law firm

Solicitors with specialist arboricultural knowledge

Practical advice focused on early resolution

Experience acting for homeowners, insurers and public authorities

Fixed fees available for many types of work

Nationwide service throughout England and Wales